What is total float (total slack) and how to total float calculate it in a network diagram
Total float is how long an activity can be delayed, without delaying the project completion date. On a critical path, the total float is zero. Total float is often known as the slack. You can calculate the total float by subtracting the Early Start date of an activity from its Late Start date.