Total float is how long an activity can be delayed, without delaying the project completion date. On a critical path, the total float is zero. Total float is often known as the slack. You can calculate the total float by subtracting the Early Start date of an activity from its Late Start date.

Total float calculate it in a Network diagram

PROJECT MANAGEMENT COURSE

Introduction to CPM network diagrams Previous post How to draw a CPM network diagram
What is total float (total slack) and how to calculate it in a network diagram Next post Free Float(free slack) calculation it in a network diagram

Average Rating

5 Star
0%
4 Star
0%
3 Star
0%
2 Star
0%
1 Star
0%

Leave a Reply

Your email address will not be published. Required fields are marked *