Start to Start (SS) network diagram example with lag

Lag in network diagrams
Page Visited: 720
0 0
Read Time:22 Second

Start to Start (SS) network diagram Lag is the delay of a successor activity and represents time that must pass before the second activity can begin. There are no resources associated with a lagLag may be found in activities with all relationship types: finish-to-startstart-to-start, finish-to-finish, and start-to-finish.

Start to Start (SS) network diagram example with lag

PROJECT MANAGEMENT COURSE

Lag in network diagrams Previous post Finish to Start (FS) network diagram example with lag
Finish to Finish (FF) network diagram Next post Finish to Finish (FF) network diagram example with lag

Average Rating

5 Star
100%
4 Star
0%
3 Star
0%
2 Star
0%
1 Star
0%

One thought on “Start to Start (SS) network diagram example with lag

  1. Good explanation, exactly what I looked for. Thanks!

Leave a Reply

Your email address will not be published. Required fields are marked *