Total float and Free float slack of activities

What is total float (total slack) and how to calculate it in a network diagram
Page Visited: 365
0 0
Read Time:23 Second

How To Determine total float and free float slack of activities in a network diagram

Total float is how long an activity can be delayed, without delaying the project completion date. On a critical path, the total float is zero. Total float is often known as the slack. You can calculate the total float by subtracting the Early Start date of an activity from its Late Start date.

PROJECT MANAGEMENT COURSE

What is total float (total slack) and how to calculate it in a network diagram Previous post Free Float(free slack) calculation it in a network diagram
Lag in network diagrams Next post Lag in network diagrams

Average Rating

5 Star
0%
4 Star
0%
3 Star
0%
2 Star
0%
1 Star
0%

Leave a Reply

Your email address will not be published. Required fields are marked *